8 retail locations that need rewired, must have current state license
Day 1: Demo any existing receptacles that would interfere with new fixture installation, all other receptacles will be made to white if not already. Installation of new wall outlets as shown on print. All receptacles/plates are to be white and jumbo plates preferred. Make outlets operable before leaving.
Day 2: Installation of outlets in fixtures as shown on plan. Data boxes are furnished and installed, but data lines run by separate contractor. Provide pull strings run thru power poles (set by us) for data contractor.
There is no lighting removal/ installation on this project
This project typically requires no more than 10 hrs. for a qualified 2 man team and between 200’- 400’ of MC cable and 20-30 duplex outlets
You will supply all MC cable, outlet boxes, receptacles and plates in white and install per plan. Clean up and haul off your debris
NC478 Whiteville – 8/13-8/14 - Agent
NC076 Ahoskie- 8/20-8/21 - Agent
NC319 Ahoskie – 8/23-8/24 - Agent
NC564 Nags Head – 8/27-8/28 – Agent
NC511 Kenansville – 9/10-9/11 - Agent
NC362 Marion – 9/20-9/21 - Agent
NC586 Lumberton – 9/13-9/14 - Agent
NC078 Lumberton – 9/17-9/18 - Agent