Entire Scope:
Migrate current IHiS SAP ECC and EP systems to IHiS H-Cloud data centre (HDC)
Apply the necessary SAP/Database prerequisite for the planned upgrade
Setup SAP Interim server for installation of SAP/Database patches
Apply SAP Application Support patches (from patch 8 to patch 18)
Apply MS SQL 2008 SP3
Perform OS/DB upgrade (from WIN/MS SQL 2008 to WIN/MS SQL 2016)
Perform SAP ECC Upgrade (from EHP5 to EHP8)
Perform SAP EP Upgrade (from SAP NetWeaver 7.02 to SAP NetWeaver 7.50)
Install new SAP Solution Manager (Solman) and SAP Router
Configure SAP ECC and EP systems to support SSL for HTTPS in IHiS HDC F5 Load Balancer
Install SFTP client and migrate current key (passcode) from current to target systems
Perform one (1) FDR (full dress rehearsal) before actual PROD system cutover